Surveys, Investigations and Detailed Design for Sub Regional Transport Enhancement Project as VO No. 4 under Road Connectivity Sector I Project – ADB
Funding Agency: Asian Development Bank
Client: Depart of Roads (DoR)/ Project Directorate (ADB)
Date: March 2010 – Dec 2010
Project Preparation and Detailed Design work for Subregional Transport Enhancement Project as VO No. 4 under Road Connectivity Sector I Project which includes fast-tracked combined feasibility study and detail engineering design of the following roads :
- Belbari-Chaurahawa (BC) (47 km in Chaurahawa-Koshi section of East-West Highway)
- Harkhapur-Okhaldhunga (HO) (41 km)
- Okhaldhunga-Salleri (OS) (58 km)
- Chainpur – Khandbari (CK) (44km)
- Bhairahawa Bypass (BBY) (3 km)
- Nepalgunj – Kohalpur (NK) (25 km)
Overall Services provided:
(a) Review and Updating of Field Survey and investigation
- Topographic Survey
- Geotechnical Survey
- Traffic and axle load survey
- Soil and Construction material investigation
(b) Preparation of Tender
(c) Detailed Engineering Design and Social Environmental Assessment (RAP/IEE/EMP)
- Preliminary design
- Detail engineering design of the selected option for improvement and upgrading of the project roads
- Cost estimation
(d) Hydraulic/Hydrological investigations and Drainage Studies
(e) Review and Updating of the Cost Estimate
(f) Review and update of contract packaging/bidding
(g) Review and Update of Financing and Economic
(h) Social Assessment Study / Resettlement Action Plan
- Assessment a